North Channel Construction Set for 2027 on Fort Worth Flood Control Project

The initial phase of the Panther Island flood control project, focusing on the north channel of the Trinity River, is slated to commence in February 2027.

By TradepilotUSA News Desk

Event · Published · 2 min read

Media: © OpenStreetMap contributors · OpenFreeMap · Peggy Greb, USDA Agricultural Research Service · USGS · Mark D, USDA Agricultural Research Service · United States. Army. Corps Of Engineers · https://www.loc.gov/pictures/item/fl0409.photos.331872p · P1898

Construction on the first phase of the Central City/Panther Island federal flood control project is scheduled to commence in February 2027, according to a report by the Fort Worth Report. This initial phase focuses on the north channel of the Trinity River bypass, a crucial component of the $1.6 billion flood control effort.

The Walsh Group, a construction company based in Chicago, has been awarded a $169 million contract to construct the first half of the bypass channel. Once completed, the north bypass will measure 3,900 feet in length and 300 feet in width at the bottom. The design includes an earthen levee and concrete floodwalls to manage the water flow within the channel.

The entire project is expected to take approximately three years to complete. It aims to redirect floodwaters from the Trinity River away from 2,400 acres of homes and businesses located in downtown Fort Worth and the Historic Northside neighborhood.

Future Developments and Community Engagement

The Corps of Engineers plans to request bids from developers by summer 2027 for the construction of the south channel. Meanwhile, the city and the water district have already initiated smaller projects related to the Central City effort. These include the restoration of natural habitats on the Ham Branch of Marine Creek to mitigate the environmental impact of the construction.

Originally, the groundbreaking for the north bypass channel was set for spring 2026. The existing 27-mile Trinity levee system, constructed by the Corps of Engineers beginning in the 1950s, is deemed insufficient for managing floodwaters expected in a city with a population of about 350,000.

Under the agreement with the water district, Fort Worth is tasked with building city-owned stormwater systems, bridges, and streets. The water district will oversee the construction of canals, walkways, and related improvements on Panther Island. The master plan for Panther Island includes a goal to preserve 15% of the area as open space.

A public improvement district has been established by the city council to alleviate the financial burden on the water district for public infrastructure upgrades and renovations. Property owners within the district will be assessed to help fund these improvements.

To mark the commencement of the north bypass channel, a groundbreaking event is being planned. Additionally, an open house is scheduled for the public to learn more about the progress of the Central City project. This event will take place at 6 p.

m. on Thursday at the Northside Community Center.